Elaboration of electric vehicle charging plan

Elaboration of electric vehicle charging plan
SUBMITTED FROM:

MUNICIPALITY OF PALAIO FALIRO

Paleo Faliro is a coastal district of the South Sector of Athens, southwest of the center of Athens. Its area is 4.6 square kilometers, while the length of its Saronikos beach is about 4 km. It is about 9 km from the center of Athens (connected to Syngrou Avenue), 13 km from the port of Piraeus (connected with Poseidonos Avenue) and approximately 40 kilometers from Athens Eleftherios Venizelos International Airport.

Paleo Faliro is located on the southern side of the prefecture of Attica and borders the municipalities of Kallithea (west-north, bounded by Syngrou Avenue), Nea Smyrni (north-northeast), Agios Dimitrios (east) and Alimos (east-southeast, bounded the Rema of Picrodaphni). The beach of Palaio Faliros is mainly south-west oriented.

www.palaiofaliro.gr



Objective Action

The aim of the initiative is the writing of the Electric Vehicle Charging Plan [1] of the Municipality of Palaio Faliro with the main aim of creating a master plan, which concerns the planning of the installation of charging stations with an implementation horizon of three (3) years in order to cover charging needs of all categories of electric vehicles for the next five (5) years.

This action aims to ensure the necessary condition for the promotion of electric mobility, i.e. a charging infrastructure network at its operational limits. The creation of infrastructure to encourage the purchase of electric vehicles which contribute to the improvement of air quality within urban centers and residential tissues.

 

[1]: In Greek the relevant initials are Σ.Φ.Η.Ο.

 

Target Audience

To all residents and drivers of electric vehicles passing through the Municipality of P. Faliro.

 

Duration

The initiative in question started in 2020 and ended in September 2021.


Description

The object of the initiative is the provision of services for the preparation of an Electric Vehicle Charging Plan (EVCP), in accordance with Article 17 of Law 4710/2020 (Government Gazette 142 A/2020) "Promotion of electric mobility and provisions", on the basis of which it becomes mandatory to locate at least one (1) electric vehicle recharging point per thousand (1,000) inhabitants within the limits of administrative responsibility of each municipality. The specific service must result in the type of chargers that will be procured by the Municipality, therefore the existence of a special officer is required to carry out the market research and in cooperation with the officers of the Municipality to come up with the right types of chargers.

Because the existing staff of the municipality does not have the know-how and specialized corresponding experience, the municipality proceeded to announce a summary tender for the provision of EVCP preparation services. In particular, the provision of the advisory - scientific support to the executives of the Working Group (WG) of the Municipality concerned the provision of a general advisory service with the object of planning, programming and organizing development action for the location of the Stations, as well as horizontal interventions, the support their implementation with the transfer of the necessary relevant know-how, as well as the provision of external services for the above stages of the preparation of the Plan.

According to Article 17 of Law 4710/2020 (Government Gazette 142 A/2020) "Promotion of electric mobility and provisions", it becomes mandatory to locate at least one (1) electric vehicle recharging point per thousand (1,000) inhabitants within the limits of administrative responsibility of each municipality. Given that the population of our municipality amounts to 64,021 inhabitants according to the last official census of 2011, at least 64 charging points are necessary.

Based on the legislation FEK 50B 2015 the acceptable methods of charging batteries of electric cars that can be installed in vehicle service facilities are method 3 (Mode 3 AC Charging) and method 4 (Mode 4 DC Charging), as defined by the standard IEC 61851−1 "Electric Vehicle Conductive Charging System". Also, the acceptable interface elements (power socket, plugs, terminals) of said charging devices are defined by the standard EN/IEC 62196-2 "Plugs Socket-outlets, Vehicle Couplers and Vehicle Inlets - Conductive Charging of Electric Vehicles".

Funding: GREEN FUND

A consultation entitled: "Public Consultation - Participatory procedures: Presentation of the prevailing scenario - expression of views of bodies" was held on November 1, 2021, through video conference, due to the coronavirus pandemic, with invited various relevant bodies such as Hellenic Electricity Distribution Network Operator (HEDNO) [2], Athens Mass Transit System (AMTS) [3], Hellenic Institute of Electronic Vehicles (HIEV)[4], etc.

At the same time, in the context of participation for the preparation of the EVCP, a special questionnaire was developed that was addressed to residents, employees and/or visitors of the Municipality (general public). A presentation of the consultation was made by the contractor where the alternative siting scenarios were analyzed and the most prevalent one was presented. The plan was then completed and actions recorded for its implementation with alternative implementation methods

The time planning of the siting/licensing of the charging points was mapped, the specifications of the proposed network of recharging points were drawn up, the financing possibilities of the action were mentioned and an incentive policy was developed at the local level.

 

 

[2] In Greek ΔΕΔΗΕ.

[3] In Greek ΟΑΣΑ.

[4] In Greek ΕΛ.ΙΝ.Η.Ο.


more...

Impact on Society

Placement of charging points for Electric Vehicles, choosing scenario 1: 64 zones with 81 charger positions.



Initiative Location

Municipality of Palaio Faliro


Working with Organization

The Municipality concluded a public contract with the company VMC TECHNIKI EE (ADAM: 21SYMV008261242) for the implementation of the action. HEDNO also contributed to the implementation of this action. An electronic meeting was held with organizations active in the region (REA Clinic[5] and Eugen Foundation), in order to contribute with their experience, opinions and comments in the process as well as to identify and/or prioritize (if any) other representative points (sub-regions) in the municipality.

 

[5] Gynecological Hospital for mothers giving birth.


More...…

Workers Participation

A Working Group was formed for the preparation of the EVCP with the No. Protocol 26104/14-12-2020 decision by the Director of Technical Department, consisting of engineers - service executives. The collaboration of the municipality's Working Group with the contractor's Project Team, as well as with the other stakeholders, was organized in a way that ensured the quality and validity of the deliverables.


More...…

Benefits for Οrganization

  • Configuration of a modern and safe framework for electric mobility
  • Development of charging infrastructure
  • Development of a road map for continuous monitoring of the study and identification of risks
  • Utilization of financial tools / the action was implemented with funding from the Green Fund
  • This action promotes to the public the spirit of protecting the environment and the message of the development of green transportation in the daily life of citizens / reduction of pollution-noise pollution, reduction of greenhouse gas emissions, and more efficient use of energy and in addition, electric mobility shows macroeconomic benefits & succeeds reduction of mobility costs.